Restoration using coir bunds. Photo Credit: Lizzie Shepherd Yorkshire Peat Partnership
Objective 2.2
On course
Work with farmers and landowners to bring all remaining degraded peatland (c.28,000 hectares) into initial restoration and management by 2035.
Funding needed
This is one of the 'transformational' objectives that does not currently have the funding needed to achieve it.
Progress
The Yorkshire Peat Partnership completed restoration works on 2,275 ha of previously damaged peatland. The total area brought into restoration by Yorkshire Peat Partnership since 2009 is now almost 30,000 ha.
Rationale
National target set by Government as part of the Protected Landscapes Targets and Outcomes Framework. The National Park’s peatlands are internationally important for wildlife (see objective 1.1) and a nationally important carbon store, with almost 78,000 ha of deep peat (>40 cm deep). But much is in a poor condition as a result of drainage installed in the 1970s and 1980s. This not only erodes the peat, releasing carbon into the atmosphere, but also contributes to downstream flooding (see 2.4) and issues with water quality (objective 1.5), exacerbated by more extreme weather events associated with climate change. The costs to society of this damaged peatland are estimated to be over £4 billion over 60 years. Restoration involves blocking up the drainage (short-term) and then restoring the habitats that most effectively sequester carbon i.e. vegetation communities dominated by Sphagnum mosses (long-term). This ‘rewetting’ helps to reduce the risks of wildfire associated with drier summers as the climate changes. So, far, natural drainage has been restored across over 27,000 ha by the Yorkshire Peat Partnership, working with the support of local landowners since 2009. Up to 36,000 ha still needs to be surveyed of which around 80% (28,000 ha) is expected to require re-wetting and long-term restoration.
Lead organisations
Yorkshire Peat Partnership
Supporting organisations
Cumbria Peat Partnership; Environment Agency; National Trust; Natural England; Yorkshire Dales National Park Authority; Yorkshire Dales Millennium Trust
Cost over 5 years
Funding shortfall