Objective 4.6
On course
Continue to reduce the visual impacts of intrusive infrastructure and equipment, including putting a further 15km of overhead power lines underground by 2028.
Progress
One scheme at Yarnbury has been completed by Northern Powergrid, removing almost 2km of overhead power lines.
A further 7 schemes are progressing through design and wayleaves and are expected to be completed by March 2028. These will result in a further 10 km of line being removed at Gunnerside, Little Asby Fell, Harberwain Rigg, Bull Pot, Barden Moor, Gayle and Widdale.
Rationale
Power and communications infrastructure are essential to local communities (see objectives 2.6, 6.3 and 6.5) but require sensitive siting. Putting the more intrusive overhead lines underground, and replacing other, highly visible infrastructure, is an immediate and permanent way to enhance the natural beauty of the National Park. This objective continues the national Ofgem programme, which is being implemented by the electricity distribution companies in consultation with the National Park Authority. It covers the time period from 2024-2028. Putting lines underground also reduces the likelihood of power outages as a result of extreme weather events associated with climate change.
Lead organisations
Electricity North West; Northern Powergrid
Supporting organisations
Yorkshire Dales National Park Authority
Cost over 5 years
Funding shortfall