Annex
Yorkshire Dales National Park
Protected Landscapes Targets & Outcomes Framework
IMAGE: The Yorkshire Dales National Park logo identifies the organisation responsible for this framework. The logo includes the text “YORKSHIRE DALES National Park”.
| PLTOF Outcome | NPMP Objective | Target end point | ||
|---|---|---|---|---|
| T1 Restore or create more than 250,000 hectares of a range of wildlife-rich habitats within Protected Landscapes, outside protected sites by 2042 (from a 2022 baseline). | A7 5,000 hectares by 2030 | 35,000 ha by 2042 | ||
| T2 Bring 80% of SSSIs within Protected Landscapes into favourable condition by 2042. | A1 45% by 2030. | 80% by 2042 | ||
| T3 60% of SSSIs within Protected Landscapes to be assessed as having ‘actions on track’ to achieve favourable condition by 31 January 2028. | A1 60% by 2028 | Same | ||
| T4 Continuing favourable management of all existing priority habitat already in favourable condition outside of SSSIs (from a 2022 baseline) and increasing to include all newly restored or created habitat through agri-environment schemes by 2042. | A3 Increase of 10,000 ha in management by 2030 | All priority habitat in management by 2042 | ||
| T5 Ensuring at least 65% to 80% of land managers adopt nature friendly farming on at least 10% to 15% of their land by 2030. | D1 At least 80% of land managers have adopted nature-friendly farming on at least 15% of their land by 2030. | Same | ||
| T6 Reduce net greenhouse gas emissions in Protected Landscapes to net zero by 2050. | D - all Net negative by 2040 at the latest. | Net negative by 2040 | ||
| T7 Restore approximately 130,000 hectares of peat in Protected Landscapes by 2050. | A2 Initial restoration of 28,000 ha by 2035 | 28,000 ha restored by 2050 | ||
| T8 Increase tree canopy and woodland cover (combined) by 3% of total land area in Protected Landscapes by 2050 (from 2022 baseline) | B3 Create of 6,000 ha of woodland by 2031 | Create 12,000 ha by 2050 | ||
| T9 Improve and promote accessibility to and engagement with Protected Landscapes for all using existing metrics in our Access for All programme | C1 Create 5 new ‘miles without stiles’ routes by 2030 C4 Engage with 5,000 school children p.a. C5 7,000 volunteer days p.a. (1,400 from under-served groups by 2029) E5 Create 5 accessibility hubs by 2030 F6 Create 2 new multi-use routes by 2030 | Same | ||
| T10 Decrease the number of nationally designated heritage assets at risk in Protected Landscapes. | D3 Reduce the number of nationally designated heritage assets at risk, so that no more than 12 are at risk by 2030. | Same |